Capital Improvement Projects (CIPs) are large, long-term investments the county makes to build, upgrade, or replace major public facilities and infrastructure. These projects usually cost more than routine maintenance and are planned years in advance because they support essential services and community growth.
Long Term and On-Going Projects
Akers Wetland Bank
From Road: Akers Drive across from Public Works Bldg.
To Road:
Current Status: Design
Start: 2022
End: TBD
Project Details: Design and Construction of wetland credits within EPC owed property, located west of Akers Drive
Project Team: El Paso County / Kimley-Horn and Associates
Road Closure: No
Detour Route: N/A
Project Type: County/Federal
Estimated Cost: $551,629-design
Project Manager: Howard Schwartz
Contact: https://citizenconnect.elpasoco.com or 719-520-6460
Project Website: N/A
Schedule: TBD
Information current as of 08/01/2026
Arnold Avenue Bridge Replacement
From Road: Mitchell Ave
To Road: Fairchild Ave
Current Status: Post-Construction Erosion Control & Mitigation Monitoring
Start: 2019
End: 2026
Project Details: Bridge replacement
Project Team: El Paso County / Alfred Benesch (design)
Road Closure: N/A
Detour Route: N/A
Project Type: Federal/County
Estimated Cost: $3,050,000 total project
Project Manager: John Lantz
Contact: https://citizenconnect.elpasoco.com or 719-520-6460
Project Website: N/A
Schedule: Design 2019-2024, Construction 2024-2025, Post-Construction/Mitigation Monitoring 2025-2028
Information current as of 09/10/2026
Arrowwood Cul-de-sacs
From Road: Sierra Way
Roads: Arapahoe Dr, Cheyenne Way, Powderhorn Dr, Calumet Rd.
Current Status: Design
Start: July 2025
End: TBD
Project Details: Cul-de-sac improvements
Project Team: El Paso County
Road Closure:No
Detour Route: N/A
Project Type: County
Allocated Funding: $200,000
Project Manager: Alissa Werre
Contact: https://citizenconnect.elpasoco.com or 719-520-6460
Project Website: N/A
Schedule: Design 2025/2026; Construction 2026
Information current as of 08/03/2026
Baptist Rd / Hodgen Rd / Roller Coaster Rd Intersection Improvements
From Road: Baptist Rd / Hodgen Rd
To Road: Roller Coaster Rd
Current Status: Design
Start: February 2025
End: Summer 2026
Project Details: Intersection improvements TBD.
Project Team: El Paso County/ Aecom Design
Road Closure: No
Detour Route: N/A
Project Type: County / PPRTA
Cost: Design $820,000
Project Manager: Omar Lopez
Contact: https://citizenconnect.elpasoco.com or 719-520-6460
Project Website: N/A
Schedule: 2025 / Construction Q2 2027
Information current as of 08/11/2026
Beacon Lite Road
From Road: Bricker Road
To Road: Wakonda Way
Current Status: Construction
Start: October 2025
End: Spring 2027
Project Details: This project includes replacing the existing gravel roadway with asphalt, realigning and regrading the road to meet criteria, and drainage improvements
Project Team: El Paso County / Michael Baker Design / Contractor – Capital Paving and Construction
Road Closure: No
Detour Route: Northbound Beacon Lite Closed at Wakonda. Follow posted detour signs.
Project Type: PPRTA
Estimated Cost: $23,000,000
Project Manager: Omar Lopez
Contact: https://citizenconnect.elpasoco.com or 719-520-6460
Project Website: https://publicworks.elpasoco.com/beacon-lite-road-project/
Schedule: Design 2019-2022, Property Acquisition 2023-2024, Construction Fall 2025
Information current as of 08/11/2026
Bradley Road Widening
From Road: South Academy Road
To Road: Hancock Expressway
Start: 2023
End: TBD
Current Status: Design
Project Details: Design and Construction of roadway improvements (widening from 2 lane to 4 lanes road) on Bradley Road.
Project Team: El Paso County/Stanley Consultants
Road Closures: No
Detour Route: N/A
Project Type: Federal/County
Estimated Cost: $1,426,414 Design
Project Manager: John Andrews
Contact: https://citizenconnect.elpasoco.com or 719-520-6460
Project Website: N/A
Schedule: Design 2023-2026; Property Acquisition 2026-2027, Construction TBD
Information current as of 08/01/2026
Briargate Parkway
From: Black Forest Road
To: Vollmer Road
Current Status: Design
Start: 2025
End: 2027
Project Details: Design and Plan Preparation for the construction of a new four-lane divided arterial roadway
Project Team: El Paso County / Wilson & Company
Road Closure: No
Detour Route: N/A
Project Type: PPRTA
Estimated Cost: $1,875,000
Project Manager: Mike Chaves
Contact: https://citizenconnect.elpasoco.com or 719-520-6460
Project Website: https://www.briargate-stapleton.com/black-forest-vollmer
Schedule: Design Complete 2027; Construction to follow
Information current as of 06/02/2026
Colorado Centre Drainage Improvements
From Road: Bradley Rd
To Road: Flagstone St
Current Status: Construction
Start: 08/01/2023
End: 2026
Project Details: This Project seeks to improve drainage capacities and conveyance methods within the Colorado Centre residential development through improvements to roadway elements and drainage facilities.
- Project map
- Colorado Center Mailer – forthcoming meeting
- Colorado Centre FAQ 01-06-2025
- Project Updates 21 February 2025
- Project Updates 26 March 2025
- Project Updates 25 April 2025
- Project Updates 06 May 2025
- Project Updates 02 June 2025
- Project Updates 05 June 2025
- Project Updates 24 June 2025
- Project Updates 01 July 2025
- Project Updates 04 August 2025
- Project Updates 12 September 2025
- Project Updates 07 October 2025
2026 - Project Updates 05 August 2026
Project Updates 28 May 2026
Project Updates 10 June 2026
Project Updates 17 June 2026
Project Updates 29 June 2026
Project Updates 07 July 2026
Project Team: El Paso County, JR Engineering (Design), FHU Engineering (CM), Native Sun Construction Inc. (Construction)
Road Closure: Horizonview Dr between Anvil Dr and Chieftan Dr.
Detour Route: Public is advised to follow detour signage and utilize Marksheffel Road and Drennan Road for inbound/outbound access to the neighborhood.
Project Type: ARPA (Federal) / County
Estimated Cost: $10,000,000
Project Manager: John Andrews
Project Contact: ColoradoCentreProject@gmail.com or 719-396-2165
County Contact: dotweb@elpasoco.com or 719-520-6460
Project Website: N/A
Schedule: Design Phase 2023-2024, Construction 2025-2026
Information current as of 08/05/2026
Constitution Ave./ Peterson Rd. Intersection
From Road: Leoti Dr
To Road: Canada Dr
Current Status: Design
Start: 2025
End: TBD
Project Information: The El Paso County Department of Public Works will hold a public information meeting Tuesday, Aug. 18, to present planned pedestrian and traffic safety improvements along Constitution Avenue between Piros Drive and Canada Drive, including work at Leoti Drive, Peterson Road and Canada Drive. The meeting will be held from 5:30 to 6:30 p.m. at the Brown Transportation Complex, 3275 Akers Drive, Colorado Springs, CO 80922.
The purpose of the meeting is to provide project information before construction begins. The informational meeting will include the planned improvements, construction schedule and expected traffic impacts.
A 2025 Traffic Impact Study recommended roadway and intersection safety changes in the corridor. Planned improvements include:
- Pavement preservation and new striping.
- A wider and longer center median at Peterson Road to reduce pedestrian crossing distances and to provide a refuge while crossing Peterson Road;
- A second northbound and southbound left-turn lane on Peterson Road at Constitution Avenue;
- Fully protected left-turn signal phases, revised signal timing and new street lighting along the approaches to and within the intersection; and
- Median changes at Leoti Drive and Canada Drive that will restrict north-south through movements and selected turns. Left turns from Constitution Avenue onto Leoti Drive and Canada Drive will remain available.
Construction is currently expected to begin in September 2026. Two-way traffic will be maintained in all directions, and single lane closures should be expected.
Project Details: Intersection improvements
Project Team: El Paso County / Alfred Benesch
Road Closure: N/A
Detour Route: N/A
Project Funding Type: County and Federal
Allocated Funding: $300,000 (design); $1,207,875 (construction)
Project Manager: Alissa Werre
Contact: https://citizenconnect.elpasoco.com or 719-520-6460
Schedule: Planning 2025; Design 2025/2026; Construction 2026
Information Current as of 08/03/2026
Deer Creek Rd / Base Camp Rd / Microscope Way
From Road: Monument Hill Road
To Road: Woodmoor Drive
Current Status: Construction Start/Mobilization
Start: 2019
End: 2027
Project Details: Roadway, intersection and drainage improvements
Project Team: El Paso County / AECOM (design)
Road Closure: N/A
Detour Route: N/A
Project Type: PPRTA
Estimated Cost: $6,000,000 total project
Project Manager: John Lantz
Contact: https://citizenconnect.elpasoco.com or 719-520-6460
Project Website: N/A
Schedule: Planning 2019, Design 2021-2025, Construction 2026
Information current as of 09/10/2026
Eastonville Corridor
From Road: McLaughlin Road
To Road: Latigo Boulevard
Current Status: Phase I – Property Acquisition/Preparing to Advertise; Phase II – Final Design Updates; Phase III – Developer-led
Start: 2020
End: TBD
Project Details:
Corridor Study complete – Traffic Impact Study/Conceptual Design Report; Phased-Approach Design Commenced:
- Phase I – Motley Rd to Londonderry Dr
- Phase II – McLaughlin Rd to Motley Rd
- Phase III – Londonderry Dr to Latigo Blvd
Project Team: El Paso County / Wilson & Company (Corridor Study)/Stanley Consultants (Design)
Road Closure: N/A
Detour Route: N/A
Project Type: PPRTA
Estimated Cost: TBD
Project Manager: John Lantz
Contact: https://citizenconnect.elpasoco.com or 719-520-6460
Project Website: https://www.eastonvilleroad.com
Schedule: Corridor Study 2020/Phase I Design 2021-2025, Construction 2026/ Phase II Design 2024-2025, Construction 2026-2027/Phase III Developer-led Design/Construction – On-Hold
Information current as of 09/10/2026
EPC Pedestrian Crossing Improvements
From Road:
To Road:
Current Status: Design
Start: 2024
End: 2026
Project Details: Design and construction of improvements to 24 intersections throughout El Paso County to improve pedestrian safety by replacing outdated signal systems, signage, striping, additional sidewalks, etc. at locations which include school crossings, access to trails, jobs, parks, transit, and other pedestrian generators
Project Team: El Paso County / HDR Engineering, Inc. (Design) / TBD (Construction)
Road Closures: Road Closures at some locations
Ped Crossing Detour King elementary Defoe Ave
Ped Crossing Detour map – Sunrise Elementary
Security and Willis Detour Map
Detour Route: N/A
Project Type: Federal
Estimated Cost: Design: $2,360,000.00 / Construction: $11,982,284.00
Project Manager: Amy Dahlberg
Contact: https://citizenconnect.elpasoco.com or 719-520-6460
Project Website: N/A
Schedule: Design 2024 – 2025 / Construction 2026
Information Current as of 08/05/2026
Fountain Creek at Hanson Trailhead
Start: May 2025
End: DEC 2027
Current Status: Preliminary Design
Project Details: Design and Construction of damaged banks within Fountain Creek by the Hanson Trailhead area
Project Team: El Paso County/Olsson
Road Closures: No
Detour Route: N/A
Project Type: County/FEMA
Estimated Cost: $796,150-Design
Project Manager: Veronica Cid
Contact: dotweb@elpasoco.com or 719-520-6460
Project Website: N/A
Schedule: Design 2025-2027
Information Current as of 08/01/2026
Furrow Road
From Road: Lamplight Rd/ Minglewood Trail
To Road: Minglewood Trail (north)
Start: 2022
End: 2026
Project Details: Design and Construction of roadway improvements
Project Information:
Mini Circular Intersections (traffic circles) will be constructed at the intersections of Furrow Road and Minglewood Trail (north) and Furrow Road and Lamplight Drive/Minglewood Trail. Construction will begin the week of August 10th with an expected construction duration of 2 weeks, weather and resource dependent. Furrow Road, between Highway 105 and Higby Rd is planned to be closed to through traffic starting August 11th or August 12th and should be open the evening of Friday, August 14th, weather and resource dependent. The signed detour will be Fairplay Rd for through traffic. One intersection will be closed at a time. Local traffic will be allowed but movement through the closed intersections will not be allowed.
In 2021, El Paso County performed a safety analysis of Furrow Road between Highway 105 and Higby Road that included the connection at Lamplight Drive/Minglewood Trail, in unincorporated northern El Paso County. The analysis provided recommendations for long-term safety improvements along this corridor. To support and encourage safety, the County determined that Furrow Road would not be opened to through traffic until safety improvements were made.
In September 2025, the County reconstructed Furrow Road between Minglewood Trail (north) and Lamplight Drive/Minglewood Trail and provided 11-foot travel lanes and a separate 6-foot-wide non-motorized facility on the west side of Furrow Road.
Public Meeting Presentation 11/19/2024
2022-08-24 FINAL Furrow Road Report
2022-08-17 Public Meeting #2 Presentation
2021-11-09 Public Meeting #1 Presentation
Project Team: El Paso County/Stantec (design)
Road Closures: Yes
Detour Route: See Detour Maps
furrow-south-intersection-detour
Project Funding Type: El Paso County / PPRTA
Estimated Cost: $543,500 (design) / $600,000 (reconstruction);
/ $500,000 (traffic circles)
Project Manager: Alissa Werre
Contact: https://citizenconnect.elpasoco.com or 719-520-6460
Project Website: N/A
Schedule: Design 2023-2025; Construction 2025/2026
Information Current as of 08/03/2026
Galley Road/ Peterson Road
From Road:
To Road:
Current Status: Design
Start: 2023
End: Design complete. Construction funding available late 2027
Project Details: Design of a structure to convey stormwater under the intersection of Galley Rd./Peterson Rd. to alleviate flooding conditions there during moderate storm events
Project Team: El Paso County / Alfred Benesch & Company
Road Closures: No
Detour Route: N/A
Project Type: Federal
Estimated Cost: Design $640,134 / Construction $7,000,000
Project Manager: Omar Lopez
Contact: https://citizenconnect.elpasoco.com or 719-520-6460
Project Website: N/A
Schedule: Design complete early 2025 / Construction funding not available until 2028/2029
Information Current as of 08/11/2026
Goldfield Drive Structure Improvements
From Road: Fontaine Blvd.
To Road: Bradley Rd.
Current Status: Utility Relocation
Start: October 2020
End: Summer 2026
Project Details: Guardrail improvements
Project Team: El Paso County / Benesch (design)
Road Closure:No
Detour Route: N/A
Project Type: County
Estimated Cost: $TBD
Project Manager: Omar Lopez
Contact: https://citizenconnect.elpasoco.com or 719-520-6460
Project Website: N/A
Schedule: Design 2022, Construction TBD
Information current as of 08/11/2026
Highway 105 Corridor
From Road: Interstate 25 east off ramp
To Road: State Highway 83
Current Status: In Progress
Start: 2011
End: TBD
Project Information: Construction of the first phase of Project B is anticipated to begin in October 2026. The work will include construction of an underground utility joint trench (Joint Trench) within the shoulder area on the north side of Highway 105 from Lake Woodmoor Drive to just west of Martingale Rd. It will cross Highway 105 just east of Lake Woodmoor Dr and will cross Briarhaven Court, Winding Meadow Drive and Furrow Road. The Joint Trench will provide a single location for telecommunication lines to relocate to in advance of roadway construction. Two-way traffic will be maintained to the extent possible with single lane closures and flagging as required.
In addition, construction for relocation of sanitary sewer, water and electric lines will be completed by the utility providers. These relocations will generally be south of Highway 105 with periodic crossings of Highway 105. Two-way traffic will be maintained to the extent possible with single lane closures and flagging as required.
The utility relocations in advance of Highway 105 road construction are necessary due to the planned widening and vertical changes to the roadway. This initial work will also significantly reduce the overall roadway construction duration.
Project Details:
The design, property acquisition, and construction for the Highway 105 corridor improvements are being accomplished in multiple phases.
Project A
Complete
Project B: The second segment of the corridor improvements, from Lake Woodmoor Drive to Martingale Drive, will generally include widening the road to 3 lanes, improving the vertical alignment, and adding shoulders and additional turn lanes and multiple retaining walls. Ongoing goals for Project B include completing final design and property acquisition to take Project B to construction.
Martingale Drive to SH-83: Preliminary design for the remainder of the corridor continues. The phasing of construction of future segments will continue to be evaluated as part of the ongoing design.
Project Team: El Paso County/HDR (design)
Road Closure: No
Detour Route: N/A
Project Type: PPRTA/Federal/County
Current Allocated Funding: $39,000,000
Project Manager: Alissa Werre
Contact: https://citizenconnect.elpasoco.com or 719-520-6460
Schedule: Project A: complete; Project B: Final Design 2021-2025, construction 2026-2028
Information current as of 08/03/2026
Mesa Ridge Parkway
From Road: Powers Blvd (SH21) / SH 16
To Road: Marksheffel Road
Current Status: Final Design Elements / Property Acquisition
Start: 2022
End: 2027
Project Details: Roadway widening, new bridge, intersection and drainage improvements
Project Team: El Paso County / Wilson & Company
Road Closure: No
Detour Route: N/A
Project Type: PPRTA
Estimated Cost: Design $1,006,452 / Construction $8,500,000
Project Manager: John Andrews
Contact: https://citizenconnect.elpasoco.com or 719-520-6460
Project Website: N/A
Schedule: Design/Property Acquisition complete early 2026. Construction complete late 2027
Information current as of 08/01/2026
North Calhan Highway
From Road: US 24
To Road: Paint Mine Road
Current Status: Design
Start: 2025
End: 2026
Project Details: Roadway, drainage and pedestrian improvements
Project Team: El Paso County / FHU (design)
Road Closure: N/A
Detour Route: N/A
Project Type: PPRTA
Estimated Cost: $7,100,000 total project
Project Manager: Mike Chaves
Contact: https://citizenconnect.elpasoco.com or 719-520-6460
Project Website: N/A
Schedule: Design 2025-2026, Construction 2027-2028
Information current as of 06/01/2026
North Gate / Struthers Drainage Improvements
From Road: Shepard Heights
To Road: I-25
Current Status: Substantially Complete, Punchlist Items & Post-Construction Activities
Start: 2015
End: 2026
Project Details:
Construction of sub-regional drainage system improvements along Struthers Road & North Gate Boulevard, including a water quality pond in the median of I-25
Project Team: El Paso County/Wilson & Co (design)
Road Closure: N/A
Detour Route: N/A
Project Type: Federal/County
Cost: $4,800,000
Project Manager: John Lantz
Contact: https://citizenconnect.elpasoco.com or 719-520-6460
Project Website: N/A
Schedule: Design 2015-2024, Construction 2025-2026
Information current as of 09/10/2026
Peyton Area Roads – Railroad, Front and Main Streets Improvements
From Road: N/A – Town of Peyton
To Road: N/A – Town of Peyton
Current Status: Preliminary Design
Start: 2020
End: TBD
Project Details: Drainage & Traffic/Transportation Infrastructure Study
Project Team: El Paso County/ AECOM (Master Plan)
Road Closure: N/A
Detour Route: N/A
Project Type: County
Estimated Cost: TBD
Project Manager: John Lantz
Contact: https://citizenconnect.elpasoco.com or 719-520-6460
Project Website: N/A
Schedule: Planning 2021-2023 / Design 2025-2027 / Construction TBD
Information Current as of: 09/10/2026
Rex and Meridian
From Road: Indian Paint Trail
To Road: Antlers Ridge Drive
Current Status: Closeout
Construction Start: 2024
Construction End:November 2024
Project Details: El Paso County has designed improvements for the Rex Road at Meridian Road Intersection north of Falcon with construction scheduled to begin in early 2024. The improvements consist of installing a traffic signal, improving sight distance, widening Meridian to four lanes and adding turn lanes on Rex with full-depth reconstruction of both Rex and Meridian roads, roadside ditch and stormwater improvements, and utility relocations.
Project Manager: Omar Lopez
Project Team: El Paso County / AECOM (design) / Contractor – ESI
Road Closure: N/A
Detour Route: N/A
Project Type: County
Cost: $9,900,000
Contact: 719-520-6460
Project website: https://publicworks.elpasoco.com/road-bridge/construction-maintenance-projects/#1600793556228-8faa25db-06a2
Schedule: Project complete
Information current as of 08/11/2026
Rex & Meridian Project | Public Meeting PowerPoint
Rex & Meridian Project | Public Meeting Display Boards
South Academy Blvd Widening
From Road: West of I-25 near Venetucci Blvd
To Road: South of Milton E Proby Pkwy
Current Status: Substantially complete
Start: September 2023
End: June 2026
Project Details: This project is a component of the Military Access, Mobility & Safety Improvements project.
The project included:
- Widening South Academy Blvd along this mile and a half stretch,
- Widening the bridges crossing over Bradley Rd,
- Scour protection to improve the resilience of bridges crossing Fountain Creek,
- Noise abatement treatments,
- Drainage improvements,
- Lighting improvements, and
- Various other infrastructure work resulting in three dedicated lanes of traffic in each direction along this section of the corridor.
Project Team: El Paso County / SEMA Construction (Construction) / AECOM (Design) / Wilson (Construction Management) / CDOT (partner)
Road Closure: No
Detour Route: N/A
Project Funding Type: PPRTA / Federal / County
Cost: $73,000,000 (total estimate)
Project Manager: Brett Hartzell
Contact:I25CO94.mamsip@gmail.com or 719-800-2162
Project Website: www.codot.gov/projects/military-access-improvements-in-se-colorado/south-academy-blvd
Schedule: The project’s construction was substantially completed in June 2026. Minor punch list work and/or landscaping work may still periodically occur, as needed.
Information current as of 09/02/2026
South Powers Extension Study
From Road: Mesa Ridge Parkway
To Road: I-25 at approximately Mile Marker 123
Current Status: Planning
Start: 2022
End: mid-2026
Project Details: Corridor Study
Project Team: El Paso County with considerable input from the City of Fountain and other stakeholders / Consultant Team – Wilson & Company
Road Closure: No
Detour Route: N/A
Project Type: CDOT Multi-Modal Options Fund funding
Cost: $1,220,000
Project Manager: Howard Schwartz
Contact: https://citizenconnect.elpasoco.com or 719-520-6460
Additional Project Team Contact: SouthPowersStudy@gmail.com
Project Website: www.southpowersstudy.com
Schedule: Study essentially complete – must update documents to Americans with Disability Act compliance and present to El Paso County Planning Commission for adoption into EPC Master Planning Document
Information current as of 01/12/2026
Ute Pass Trail Phase 2 Project
From Road: Winnemucca Road
To Road: US 24 & Fountain Ave Intersection
Start: Nov 2020
End: Dec 2026
Current Status: Construction
Project Details: Construction 1.67 miles of trail along Chipita Park Road, Fountain Avenue and Springs Street from Winnemucca Road to US 24 and Fountain Avenue Intersection. Project is about 50% complete as of July 30, 2026.
Project Team: El Paso County/ AA Construction Company
Road Closures: No
Detour Route: N/A
Project Type: County/Federal
Estimated Cost: $972,000-Design
Project Manager: Veronica Cid
Contact: dotweb@elpasoco.com or 719-520-6460
Project Website: N/A
Schedule: Design 2020-2025; Construction-2026
Information Current as of 08/01/2026
Vollmer and Burgess Intersection Improvements
From Road: Vollmer Road/Burgess Road
To Road: Vollmer Road/Burgess Road
Start: March 2026
End: TBD
Current Status: Design
Project Details: Design and Construction of intersection improvements
Project Team: El Paso County/ Olsson Inc.
Road Closures: No
Detour Route: N/A
Project Type: County/PPRTA
Estimated Cost: $765,384-design
Project Manager: Veronica Cid
Contact: dotweb@elpasoco.com or 719-520-6460
Project Website: N/A
Schedule: TBD
Information Current as of 08/01/2026
Vollmer and Shoup Intersection Improvements
From Road: Vollmer Road/Shoup Road
To Road: Vollmer Road/Shoup Road
Start: 2023
End: TBD
Current Status: Preliminary Design
Project Details: Design and Construction of intersection improvements
Project Team: El Paso County/ Wilson & Company
Road Closures: No
Detour Route: N/A
Project Type: County
Estimated Cost: $776,001 -Design
Project Manager: Veronica Cid
Contact: https://citizenconnect.elpasoco.com or 719-520-6460
Project Website: N/A
Schedule: Design 2023-2026; Property Acquisition 2026; Construction TBD
Information current as of 08/01/2026
Woodmoor Dr. / Lake Woodmoor Dr. Intersection
From Road: Woodmoor Drive
To Road: Lake Woodmoor Drive
Current Status: Design
Start: 2024
End: TBD
Project Details: Intersection improvements.
Traffic study is available at link: Woodmoor Traffic Study
Project Team: El Paso County / Alfred Benesch (Design)
Road Closure: N/A
Detour Route: N/A
Project Type: County and PPRTA
Allocated Funding: $700,000 (design)
Project Manager: Alissa Werre
Contact: https://citizenconnect.elpasoco.com or 719-520-6460
Schedule: Planning 2024/2025; Design 2025/2026, Construction 2026/2027
Information Current as of: 08/03/2026